What changed after 30 September 2026
On 30 September 2026, Romania submitted its final payment request under the National Recovery and Resilience Plan to the European Commission. According to the responsible minister’s statement, reported by AGERPRES, the request covers 104 milestones and targets and seeks approximately €4.35 billion net: around €2.58 billion in grants and €1.77 billion in loans. These figures are the amount requested, not a payment already approved.
Submitting the request ends Romania’s payment-request submission stage, but does not automatically confirm that all targets have been met or trigger immediate transfer of the full amount. The European Commission must assess the evidence and satisfactory fulfilment of milestones and targets before deciding on payment.
The EU timetable and project close-out
The general Recovery and Resilience Facility timetable set 31 August 2026 as the deadline for meeting milestones and targets, 30 September 2026 for submitting final payment requests, and 31 December 2026 for completing EU payments. These dates describe the EU-level facility framework; they do not by themselves extend an individual contract or replace instructions from the national coordinator.
In Romania, Law No. 183/2026 and the information published by the Mureș County Prefect’s Institution describe operational close-out steps. According to that notice, coordinators classify investments by 31 October 2026 based on their status at 31 August, and approve the lists by 15 November. For certain categories of unfinished investments, the law provides for completion by 31 December 2026 using own and/or other legally established sources; this period does not extend the eligibility of RRP expenditure.
What beneficiaries should check now
- Ask the reform or investment coordinator to confirm the project’s classification and applicable instructions; do not infer project status solely from the national request being submitted.
- Check the contract and amendments, physical and financial status as of 31 August 2026, committed indicators, acceptance documents and transfer requests.
- If the project falls into a category that must continue using other sources, confirm the source, schedule and responsibilities in writing before committing expenditure.
- Keep supporting documents and separately track reporting, monitoring and durability obligations that continue after funding closes.
These checks are a practical orientation list, not a legal interpretation applied to a specific contract. Project classification, expenditure eligibility and any recovery obligations depend on the law, contract, coordinator decisions and project documents.